Taco Bell
Daleville, VA
If you are interested in re-imaging your fast food restaurant, consider using our panel system. It can be installed in one week regardless of weather conditions and the location does not need to be closed at any time during our install. We work in the drive-thru area during early morning hours keeping your sales at their normal levels.
​
The entire installation, including the stone at the bottom took a 4 man crew 5 days to complete. The temperature onsite stayed in the upper 20s, low 30s throughout the entire job.
Building Code
-
NFPA 285 & 286 (Types I-IV)
-
IBC 2009, 2012 and 2015
– Chapter 7: Fire Resistance Rated Construction
– Chapter 16: Structure – Traverse Wind Load Resistance
– Chapter 26: Type I-IV Noncombustible -
IECC 2009, 2012 and 2015
– Chapter 4: Continuous Air Barrier -
IGCC 2012
– Chapter 4: Continuous Air Barrier
– Section 606
– Alternative Compliance Path: ASHRAE 189.1-2009
Efficiency Standards
-
ASHRAE Energy Standards Compliance
– ASHRAE 90.1 – 2007 and 2010
– Section 5: Continuous Air Barrier -
Green Building Standards Compliance
– ASHRAE 189.1 – 2009 Normative Appendix B -
LEED Eligibility: New Construction (NC) Categories:
– Energy and Atmosphere (EA)
– Materials and Resources (MR)
– Innovation in Design (ID)
Test Protocols
-
ASTM E330: Structure Pre-set at 50% / 25 psf.
-
ASTM E283: Air Leakage at 6.24 psf.
-
ASTM E331: Static Water Resistance – Two hours at 6.24 psf.
-
ASTM E331: Static Water Pressure – 15 minutes at 8, 10, and 12 psf.
-
AAMA 501.1 : Dynamic Water Resistance at 12 psf.
-
ASTM E330: Structure Performance – 100% Design Pressure at 50 psf.
-
ASTM E330: Structure Performance – 150% Design Pressure at 75 psf.